On the night of October 19, eastbound I-4 will fully close between ChampionsGate Boulevard and SR 429 from 11 p.m. to 5 a.m. FDOT's detour takes drivers off at Exit 58 onto CR 532 eastbound. From there they turn left onto Old Lake Wilson Road, drive north about two miles, turn left onto Sinclair Road, and get back on the interstate by way of SR 429. That loop runs right along Reunion's edges.
Each road on that detour is also on Osceola County's or FDOT's list to be widened. None of those widenings has finished. The busiest stretch of the loop, Old Lake Wilson Road between CR 532 and Sinclair, is still waiting on a construction start the county lists for fiscal year 2028. In the next few years, the I-4 work will reach Reunion's local streets first as detour traffic, and only later as wider pavement.
The Map, in the Order Things Arrive
The Reunion East and Reunion West Community Development Districts put a "Nearby Road Improvement Projects" table in their October 8, 2026 meeting agenda, marked current as of September 14, 2026. The table covers the projects around the community, I-4 and the local roads alike. Below are the ones on this month's detour route and the projects connected to them, each with its agency's published timeline, sorted by when they reach the pavement.
| Project | Where it touches Reunion | Status and published timeline |
|---|---|---|
| Moving I-4 Forward Project 2 | I-4 east of CR 532 to west of World Drive, including the SR 429 interchange | $582 million contract; overnight closures scheduled this month |
| CR 532 / Osceola-Polk Line Road widening | Lake Wilson Road to US 17/92, immediately south of Reunion | Estimates run from 2027 to early 2029 |
| Old Lake Wilson Road widening | CR 532 to Sinclair Road | County segment anticipated to start in fiscal year 2028 |
| SR 538 Poinciana Parkway extension | Ronald Reagan Parkway to CR 532 | Construction expected mid-2027, completion estimated mid-2030 |
| Sinclair Road extension and Poinciana Connector | West and southwest of Reunion | Sinclair in design and unfunded; Poinciana Connector in design |
The interstate is first in line. Every later row is a local road, and those are the roads now carrying the interstate's overflow.
What This Month's Closures Look Like on the Ground
FDOT has posted two closures for the second half of October. Both send traffic onto roads around Reunion.
- October 19, 11 p.m. to 5 a.m. All eastbound I-4 lanes close from ChampionsGate Boulevard to SR 429. Eastbound drivers detour along CR 532, Old Lake Wilson Road, and Sinclair Road, then take SR 429 southbound to Exit 1 and the I-4 East on-ramp. Drivers headed for SR 429 northbound follow the same route and turn onto Connector Road near Sinclair.
- October 22, overnight from midnight to 5 a.m. Both I-4 on-ramps from southbound SR 429 close. FDOT's detour runs along Sinclair Road, Old Lake Wilson Road, and CR 532.
These are overnight windows, posted on FDOT's Moving I-4 Forward closure page on October 11. Both detours use the same three local roads, so late-night drives home from the airport or a dinner out may run past orange barrels on Old Lake Wilson rather than on the interstate.
Why the Interstate Moves First
I-4 is going first because it has the money and a contractor. In April, Lane Construction Corporation announced that FDOT had picked its team as the preferred team for a $582 million design-build contract on Moving I-4 Forward Project 2. The project rebuilds 3.1 miles of I-4 from east of CR 532 to west of World Drive. It reconfigures the SR 429 interchange and adds new ramps to and from SR 538, the Poinciana Parkway. When it's finished, I-4 will have four general-use lanes and two express lanes in each direction, with direct connectors between I-4, SR 429 and SR 538.
This stretch has been under construction before. The diverging diamond interchange at I-4 and CR 532 in ChampionsGate opened to traffic in July 2022 and reached final completion in early 2023. A follow-up project added auxiliary lanes between CR 532 and SR 429, doubled the CR 532 westbound exit and eastbound entrance ramps to two lanes, and resurfaced SR 429 from I-4 to Sinclair Road. FDOT lists that work as completed in March 2024. Project 2 is the third round on the same interchanges, and it's the largest so far.
Old Lake Wilson Road Runs on Two Clocks
Old Lake Wilson Road carries about two miles of the October 19 detour, from CR 532 north to Sinclair. The plan to widen it is also the most complicated item on the list. According to Osceola County's project page, the roughly 2.5-mile stretch from CR 532 to Sinclair Road is split at Assembly Court. The county is responsible for the part from CR 532 to Assembly Court. FDOT is responsible for the part from Assembly Court to Sinclair, which includes the bridge over I-4.
The two segments run on different schedules. FDOT's half is part of Project 2, and Lane's announcement lists widening Old Lake Wilson Road from two to four lanes, with sidewalks and bicycle lanes on both sides. FDOT's project description adds a second bridge over I-4. The county page was last updated September 18, 2026. It calls the county's segment fully funded, with construction anticipated to start in fiscal year 2028, subject to Board approval and funding availability. The same page includes a new traffic signal at Spine Road. The southern half, closest to CR 532, is the one still waiting for a construction start.
That southern half is also the first piece of Old Lake Wilson that this month's detour uses. Drivers coming off CR 532 head north from there for about two miles to reach Sinclair.
CR 532 Has Three Published Finish Dates
The widening of CR 532, the Osceola-Polk Line Road just south of Reunion, is in a stage between Old Lake Wilson and I-4. It's funded and scheduled, but the finish date depends on which document you read. The Central Florida Expressway Authority describes about three miles of widening from Lake Wilson Road to US 17/92. The plans double capacity and add buffered bike lanes, a sidewalk, and a shared-use path. CFX's Spring 2026 fact sheet puts the cost at $51.88 million and lists the construction window as April 20, 2026 through 2028. CFX's project page splits the cost one-third CFX and two-thirds Osceola County, and it estimates completion in early 2029. One contractor's portfolio lists an estimated 2027 finish for the same job.
So the published estimates span about two years, from 2027 to early 2029. As of this writing, CFX's project page shows no active project alerts. CR 532 is also the first leg of both October detours, so traffic that I-4 sends off at Exit 58 starts on a road that's still two lanes.
The Projects Still on Paper
Three more projects could change how Reunion connects to the region. None of them has a shovel in the ground.
The SR 538 Poinciana Parkway extension would run 3.1 miles from Ronald Reagan Parkway to CR 532, with tolled ramps at CR 532. CFX expects construction to begin in mid-2027 and estimates completion in mid-2030. Moving I-4 Forward Project 5, the Poinciana Connector, is a separate road of about 2.6 miles. It would be a new limited-access road from CR 532 to I-4 and SR 429, with ramps to CR 532. FDOT says design is still underway. Both would bring more traffic onto CR 532 as entry points, which adds to what's at stake in that road's widening schedule.
The Sinclair Road extension would build a four-lane divided road from Tradition Boulevard to Bella Citta Boulevard, west and southwest of Reunion, with connections along Goodman Road, Bella Citta Boulevard and Tradition Boulevard. Osceola County's page, last updated May 20, 2026, says the project is in design and construction is not currently funded. The extension is a different stretch from the part of Sinclair Road that this month's detours use to reach SR 429. Like the county's Old Lake Wilson segment, though, it's a local connection that the interstate schedule is well ahead of.
Where the Schedule Gets Updated
Each of these timelines comes from the agency's own estimate, and each could move. The CDD's nearby-projects table lists a project contact and website for every project, which makes it a handy one-page reference. For nightly closures and detours, FDOT's Moving I-4 Forward site posts closure notices with exact hours and turn-by-turn detour routes. The CR 532 schedule is posted on CFX's project page, and the Old Lake Wilson schedule on Osceola County's project page. The county's next update on Old Lake Wilson will show whether fiscal year 2028 still holds.
If you own a home along Old Lake Wilson Road or CR 532 and want to know how these construction timelines could affect a decision to sell, buy or stay, Core4 Group is glad to walk you through them, segment by segment. Book a Consultation and we'll look at your street and its projects together.